Arakawa gum rosin derivatives construction project will be complete in January 2010

Rosinnet
12/30/2009
Read count:1938
Read fonts 【 large medium small

After the project started to construct in June of 2009, so far the total investment has completed 75%, the construction of the project will be finish in January 2010 and production facility will begin to install in March.

The project is invested by Arakawa of Japan with more than 100 million RMB Yuan and cover 20 thousand square meters.

Wuzhou is one of traditional gum rosin producing area in Guangxi with annual output of 100 thousand Mt. It is one of the biggest gum rosin producing base in China.